"Wait" for a specified time period?

In an orchestration job, is there a way to have Matillion just wait for some specified time period, between the completion of one component and starting the next component?

I'm thinking of having Matillion make an API call to trigger a refresh of one of my Power BI datasets. Then, I'd like to wait about 10 minutes (to let the Power BI refresh finish)...then, make another API call to trigger a refresh of a different Power BI dataset. To avoid having the two datasets in my Power BI capacity refreshing simultaneously.

1 Community Answers

Matillion Agent  

Ian Funnell —

Hi Kevin,

There’s no specific component but you could use a bash script with

sleep 60

to sleep for 1 minute.

There’s a timeout on the component so you could put it in a loop 10 times…

Best regards,
Ian